The corer and verti-drain were used on the Happy Valley turf track to alleviate surface compaction according to the following schedules:
8 – 21 April |
A to C Course (Worked Back Position) |
28 April – 4 May |
C+3 Course (Worked Back Position) and the remaining area |
On completion of the works, the areas were lightly rolled as per previous practice.