Horse Racing
Season
Renovation works - Sha Tin turf track and large all weather track

24/10/2017 18:21

1. Coring and verti-drain on Sha Tin turf track

The corer and verti-drain were used on the Sha Tin turf track to prepare for winter grass seeding from 23 to 24 October. On completion of the works, the areas were lightly rolled as per previous practice.

2. Ripping of large all weather track

The large all weather track was ripped today to a depth of 5 1/2″ to relieve surface hardness as well as to achieve thorough mixing of 140 cubic metres of bark chip applied on 23 October.