The verti-drain and the corer were used on the Happy Valley turf track to alleviate surface hardness according to the following schedules:
8 – 15 Feb | A to B Course (Worked Back Position) |
22 – 26 Feb | C Course (Worked Back Position) and the remaining area |
On completion of the works, the areas were lightly rolled as per previous practice.